PG&E Pipeline Safety

ORA's Motion for CPUC Rule 1 Violation

 

Background

 

On December 16, 2015, ORA filed a Motion with the CPUC requesting that PG&E show cause as to why it should not be sanctioned for intentional misrepresentations of its compliance with gas safety regulations. ORA asserts that PG&E should also be sanctioned for failure to have a comprehensive gas pipeline "test and replace" plan in place, as required by state law. 

  

See ORA's December 16, 2015 Motion. 

  

 

Responses

On December 30, 2015, PG&E issued a Response to ORA's Motion.  

PG&E's December 30, 2015 Compliance Letter to the CPUC:  Response to Safety and Enforcement Division Directive to Correct PG&E’s Annual Reports
 

See ORA's January 11, 2016 Reply to PG&E's Response to ORA's Motion.  

 

 

Proceeding

See the Proceeding docket.  

 

   

 

Resources

PG&E PHMSA 2014 7100 Report Update to Parts Q & R